Paglalarawan sa produksyon ng pabrika ng brick machine
a. Raw material use wheelloader delivery into batching machine , need 1 worker
b. Cement delivery into mixer, from cement silo by cement screw conveyor (
c. Mixer mixing material, then delivery to brick machine (9) by conveyor here need 1 worker
d. After produce blocks, block receiver , delivery blocks to stacker
e. Forklift ( delivery blocks to curing area , need 1 worker
f. Curing area : Curing need 10-15 days, then take blocks out from pallet; need 1-2 workers
g. After curing, take blocks out from pallet, pallet delivery to Pallet feeding machine by forklift
Blocks laying in block stock area
h. Sell blocks: Sell blocks and management; 1 worker